Woodlands School (SKANSKA)

Client: Skanska
Site: Woodlands School, Basildon
Contractor: Reactive Integrated Services
Type of works: Asbestos Removal and Land Remediation
Programme: 16 Weeks
Value: £700,000

Description of Works:

The works involved the removal of all asbestos containing materials and full demolition of the buildings.

The main asbestos removal works were within the ceiling voids. Above the ceiling finish was asbestos insulation board to structural steel beams. This was over 3 floors.

Works were completed under fully controlled conditions utilised enclosures under negative pressure. The works were completed on time and on budget.

On completion of the asbestos removal we undertook a 12 week demolition programme and all works ran completely to schedule.